For about two years now, a norm has emerged on the Mingle team: “Every story is 4 points.” As a BA on our team, I quipped, “Well, that’s because our BAs are particularly good at writing stories.” :)... And then started digging into data to understand why.
I created two charts below using data from one of Mingle’s previous releases and found them to be strikingly similar.
This chart maps the story count over 3 months for a release:
This chart maps story points over 3 months for a release:
Aside from the Y-axis scale, can you tell any obvious difference? I bet not.
Similar story sizes was the result of the conversations on our estimation sessions. This contributed to the similarity of the earlier burn up charts.
Applying normal distribution to story points, standard deviation decreases as the sample size grows.
Forecast of story count vs. story point, 2 weeks out
Forecast of story count vs. story point, 1 month out
Forecast of story count vs. story point, 3 months out
Looking at our data, we didn’t find any additional value that story points provided us (related to progress tracking). As such, we have transitioned from story points to story count:
We use a 1-2-4-8 scale, with 8 as our threshold. Anything estimated bigger than 8 becomes a placeholder for further breaking down.
Below is the distribution of our estimates used in the burn up charts on the previous page.
We believe that the key to progress reporting is not an “accurate” prediction, but visible signals that we can act on. We look to our burn-up chart to tell us: “Hey, it looks like we might not be able to get everything done by the expected date. Let’s have a conversation.
It has resulted in these two significant benefits:
Yes, the estimation column is empty! As the estimation points had naturally phased out of our process, we had an explicit conversation during our retrospective about whether or not we should reinstitute them. We decided not to, and have been happy with it.
In summary, I would like to quote Martin to support our decision: “So whenever you're thinking of asking for an estimate, you should always clarify what decision that estimate is informing. If you can't find one, or the decision isn't very significant, then that's a signal that an estimate is wasteful."